About project

Client: NIW/Farrans

Project: Carniny Road Storm Sewer

Our Task Was

As part of NIW’s Sewer Framework we were tasked by Farrans to install a new storm sewer. This consisted of a mixture of Class H 525mm pipe and 315mm uPVC pipe at a range of depths from 2m to 5m through a variety of ground conditions including rock and silty clays. Associated works included over-pumping and connection of existing network, pre-cast concrete manhole chambers and outlet headwall. All works were carried out in accordance with Scottish Standard Specification for Water and Sewerage Schemes.